Questions # 11:

A national company with offices in every state in the country has deployed a solution to allow employees to view their health benefits online. The business analyst on the project team is validating solution results to assess whether or not the solution has achieved the desired business result.

Which is the best technique to gather information from employees regarding their satisfaction with the solution?

Options:

A.

Survey

B.

Focus groups

C.

Interface analysis

D.

Organization modeling

Expert Solution
Questions # 12:

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

Options:

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Expert Solution
Questions # 13:

A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.

Which of the following types of surveys would be most appropriate to create and why?

Options:

A.

A closed-ended survey to pose several multiple-choice questions and ask the users if the current business process Is correct

B.

A closed-ended survey using the Likert scale to rank specific areas of the current business process

C.

An open-ended survey to allow users the opportunity to explain their opinions on the current business process

D.

An open-ended survey to collect different opinions on the current business process

Expert Solution
Questions # 14:

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Expert Solution
Questions # 15:

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

Options:

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Expert Solution
Questions # 16:

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?

Options:

A.

Risks identified in the risk management plan were not addressed properly.

B.

There is no issue since the product exceeded the customer expectations.

C.

The sponsor approved the release of the product without reviewing the budget.

D.

Requirements were not properly traced and monitored.

Expert Solution
Questions # 17:

A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?

Options:

A.

Storyboard

B.

Project charter

C.

Business case

D.

Survey

Expert Solution
Questions # 18:

A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.

What could have caused the documentation to be returned?

Options:

A.

The analyst did not include the scope document in the acceptance criteria paperwork.

B.

The analyst failed to gather any baseline information.

C.

The analyst performed forward and backwards traceability.

D.

The analyst utilized user stories as a requirements document tool.

Expert Solution
Questions # 19:

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

Options:

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Expert Solution
Questions # 20:

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.

Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?

Options:

A.

review with appropriate stakeholders

B.

A project management plan

C.

A risk plan

D.

A strategies and goals analysis

Expert Solution