Questions # 61:

Which of the following statements are not true about Gantt Charts, Resource Histograms and Work Breakdown Structures?

Select ALL that apply.

Options:

A.

Critical activities can be identified using Gantt Charts

B.

A Work Breakdown Structure will help to produce a clear list of individual tasks involved to complete each project element

C.

Statement of Work (SOW) outlines the objectives against which Work Packages must be measured

D.

Work Breakdown Structures cannot be used to determine resource requirements

E.

Gantt Charts clearly identify key activities that must be completed before others begin

F.

Resource Histograms are particularly useful where there are complicated resources to manage

G.

Resource Histograms graphically show the resources required over the term of the project

Expert Solution
Questions # 62:

As part of a project to refurbish a large hotel chain, the wiring of the computer network was subcontracted to a specialist IT organisation. In relation to managing risk in the project this approach can be referred to as:

Options:

A.

Reduce

B.

Avoid

C.

Transfer

D.

Accept

Expert Solution
Questions # 63:

Which type of culture, according to Charles Handy, is identified by an individual's tasks being clearly defined and their power coming from their position in the hierarchy? 

Options:

A.

Power Culture

B.

Task Culture

C.

Role Culture

D.

Person Culture

Expert Solution