Questions # 121:

An input used in developing the communications management plan is:

Options:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Expert Solution
Questions # 122:

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Expert Solution
Questions # 123:

Co-location is a tool and technique of:

Options:

A.

Develop Human Resource Plan.

B.

Manage Project Team.

C.

Develop Project Team.

D.

Acquire Project Team.

Expert Solution
Questions # 124:

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Expert Solution
Questions # 125:

Tools and techniques used for Plan Communications include the communication:

Options:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Expert Solution
Questions # 126:

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Expert Solution
Questions # 127:

Which tools or techniques are used in the Plan Schedule Management process?

Options:

A.

Benchmarking, expert judgment, and analytical techniques

B.

Statistical sampling, benchmarking, and meetings

C.

Negotiations, pre-assignment, and multi-criteria decision analysis

D.

Expert judgment, analytical techniques, and meetings

Expert Solution
Questions # 128:

An input to the Identify Risks process is the:

Options:

A.

Risk register.

B.

Risk probability and impact assessment.

C.

Communications management plan.

D.

Risk management plan.

Expert Solution
Questions # 129:

The following is a network diagram for a project.

Question # 129

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Expert Solution
Questions # 130:

Which of the following lists contain processes that are included within Project Procurement Management?

Options:

A.

Plan purchases and acquisitions, plan contracting, request seller responses, select sellers

B.

Plan purchases and acquisitions, request seller responses, select sellers, schedule control

C.

Plan purchases and acquisitions, acquire project team, request seller responses, select sellers

D.

Plan purchases and acquisitions, acquire project team, contract approval, select sellers

Expert Solution
Questions # 131:

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Expert Solution
Questions # 132:

A contract management plan is a subsidiary of what other type of plan?

Options:

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Expert Solution
Questions # 133:

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

Options:

A.

cultural differences of team members

B.

possibility of communication misunderstandings

C.

costs associated with travel

D.

costs associated with technology

Expert Solution
Questions # 134:

Quality metrics are an output of which process?

Options:

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Expert Solution
Questions # 135:

Which type of analysis is used to develop the communications management plan?

Options:

A.

Product

B.

Cost benefit

C.

Stakeholder

D.

Research

Expert Solution