Questions # 76:

Which activity involves ensuring that the composition of a projects configuration items is correct?

Options:

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Expert Solution
Questions # 77:

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Expert Solution
Questions # 78:

Which defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Expert Solution
Questions # 79:

Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

Options:

A.

Earned value performance

B.

Trend analysis

C.

Cost-benefit analysis

D.

Variance analysis

Expert Solution
Questions # 80:

When managing a project team, what helps to reduce the amount of conflict?

Options:

A.

Clear role definition

B.

Negotiation

C.

Risk response planning

D.

Team member replacement

Expert Solution
Questions # 81:

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Expert Solution
Questions # 82:

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Expert Solution
Questions # 83:

Which process group contains the processes performed to finalize all activities?

Options:

A.

Planning Process Group

B.

Executing Process Group

C.

Monitoring and Controlling Process Group

D.

Closing Process Group

Expert Solution
Questions # 84:

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Expert Solution
Questions # 85:

In which of the following types of organizations is resource availability moderate to high?

Options:

A.

Weak matrix

B.

Balanced matrix

C.

Strong matrix

D.

Projectized

Expert Solution
Questions # 86:

Inputs to the Define Activities process include:

Options:

A.

Project scope statement, resource calendars, and work performance information.

B.

Scope baseline, enterprise environmental factors, and organizational process assets.

C.

Project scope statement, approved change requests, and WBS dictionary.

D.

Scope baseline, enterprise environmental factors, and activity duration estimates.

Expert Solution
Questions # 87:

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Project document updates

B.

Organizational process assets updates

C.

Change requests

D.

Deliverables

Expert Solution
Questions # 88:

In complex projects/ initiating processes should be completed:

Options:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Expert Solution
Questions # 89:

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Expert Solution
Questions # 90:

Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?

Options:

A.

Configuration definition, configuration status accounting, configuration monitoring and control

B.

Configuration identification, configuration status accounting, configuration verification and audit

C.

Configuration identification, configuration status reporting, configuration verification and audit

D.

Configuration definition, configuration status reporting, configuration monitoring and Control

Expert Solution
Viewing page 6 out of 16 pages