Questions # 16:

Which of the following are the components of the scope baseline?

Options:

A.

Project charter, project scope statement, and work breakdown structure (WBS)

B.

Project charter, project management plan, and plan procurement

C.

Project scope statement, work breakdown structure (WBS), and WBS dictionary

D.

Project management plan, plan procurement, and contract administration

Expert Solution
Questions # 17:

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

Options:

A.

Collaboration

B.

Negotiation

C.

Decision making

D.

Influencing

Expert Solution
Questions # 18:

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Expert Solution
Questions # 19:

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Options:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Expert Solution
Questions # 20:

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Expert Solution
Questions # 21:

Using the following data, what is the Schedule Performance Index (SPI)?

EV= $500 PV= $750 AC= $1000 BAC= $1200

Options:

A.

0.67

B.

1.5

C.

0.75

D.

0.5

Expert Solution
Questions # 22:

What is the term assigned to products or services having the same functional use but different technical characteristics?

Options:

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Expert Solution
Questions # 23:

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Expert Solution
Questions # 24:

Which of the following makes changes to formally control documentation to reflect modified or additional ideas or content?

Options:

A.

Defect repair

B.

Updates

C.

Corrective action

D.

Performance reports

Expert Solution
Questions # 25:

Overlooking negative stakeholders can result in a/an:

Options:

A.

decreased likelihood of conflicting interests between stakeholders.

B.

decreased likelihood of the projects progress being impeded.

C.

increased likelihood of project failure.

D.

increased likelihood of project success.

Expert Solution
Questions # 26:

Outputs from constituent processes might be used as:

Options:

A.

Inputs to other processes.

B.

Proof of process completion.

C.

Identification of project tasks.

D.

Indicators to eliminate project redundancies.

Expert Solution
Questions # 27:

The precedence diagramming method (PDM) is also known as:

Options:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Expert Solution
Questions # 28:

Which of the following is a tool and technique used in all processes within Project Integration Management?

Options:

A.

Records management system

B.

Expert judgment

C.

Project management software

D.

Issue log

Expert Solution
Questions # 29:

Which of the following buffers protects the target finish date from slippage along the critical chain?

Options:

A.

Critical buffer

B.

Project buffer

C.

Duration buffer

D.

Feeding buffer

Expert Solution
Questions # 30:

Which is an input to the Verify Scope process?

Options:

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Expert Solution