Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the PMI Project-Management-Professional PMI-001 Questions and answers with ValidTests

Exam PMI-001 All Questions
Exam PMI-001 Premium Access

View all detail and faqs for the PMI-001 exam

Viewing page 5 out of 16 pages
Viewing questions 61-75 out of questions
Questions # 61:

The following chart contains information about the tasks in a project.

Question # 61

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Expert Solution
Questions # 62:

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Expert Solution
Questions # 63:

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

Options:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

Expert Solution
Questions # 64:

During which process does the project team receive bids and proposals?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Expert Solution
Questions # 65:

At the start of a typical project life cycle, costs are:

Options:

A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Expert Solution
Questions # 66:

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Expert Solution
Questions # 67:

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Expert Solution
Questions # 68:

Which enterprise environmental factors are considered during Estimate Costs?

Options:

A.

Market conditions and published commercial information

B.

Company structure and market conditions

C.

Commercial information and company structure

D.

Existing human resources and market conditions

Expert Solution
Questions # 69:

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Expert Solution
Questions # 70:

Labor, materials, equipment, and supplies are examples of:

Options:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Expert Solution
Questions # 71:

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Expert Solution
Questions # 72:

The three types of estimates that PERT uses to define an approximate range for an activity’s cost are:

Options:

A.

Parametric, most likely, and analogous.

B.

Least likely, analogous, and realistic.

C.

Parametric, optimistic, and pessimistic.

D.

Most likely, optimistic, and pessimistic.

Expert Solution
Questions # 73:

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

Options:

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

Expert Solution
Questions # 74:

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Expert Solution
Questions # 75:

A procurement management plan is a subsidiary of which other type of plan?

Options:

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Expert Solution
Viewing page 5 out of 16 pages
Viewing questions 61-75 out of questions