Questions # 111:

A business analyst (BA) asks participants in a workshop to write down their ideas about the feature being built on sticky notes place them on the wan and then group the ideas into similar themes. The BA is using, this technique to:

Options:

A.

prioritize requirements.

B.

prepare for requirements elicitation.

C.

identify organizational capabilities.

D.

manage stakeholder collaboration.

Expert Solution
Questions # 112:

A business analyst (BA) is preparing a governance approach. The BA is trying to define the approval process. Which factors should the BA consider?

Options:

A.

The organizational culture and type of information being approved

B.

The associated risks of foregoing or delaying an approval

C.

The formality and rigor of the prioritization process

D.

The solution performance measures

Expert Solution
Questions # 113:

You are the business analyst for your organization and you are completing the verify requirements process. There are eight characteristics each requirement should have: cohesive, complete, consistent, correct, and feasible.

Which one of the following four is not a characteristic of a requirement?

Options:

A.

Functional

B.

Modifiable

C.

Unambiguous

D.

Testable

Expert Solution
Questions # 114:

Some of the requirements in the solution must be completed because of laws and regulations in your industry. Management would like you, the business analyst, to rank the requirements according to the relevant laws.

What type of requirements prioritization is management having you complete?

Options:

A.

Regulatory ranking

B.

Business value ranking

C.

Constraint ranking

D.

Risk ranking

Expert Solution
Questions # 115:

You are the business analyst for a large project for your organization. Your project has 65 stakeholders and this will greatly increase the complexity of the communication in this project. To demonstrate how complex this project and its communication will be, you show the management the number of communication channels in this project.

How many channels exist in this project based on the number of stakeholders?

Options:

A.

2080

B.

4160

C.

4225

D.

65

Expert Solution
Questions # 116:

Paul is the business analyst for his organization. He is examining a single solution to determine if the solution he and his team have identified carries enough business value to justify its implementation.

What business analysis process is Paul performing in this scenario?

Options:

A.

Define transition requirements

B.

Assess proposed solution

C.

Assess organizational readiness

D.

Allocate requirements

Expert Solution
Questions # 117:

You are the business analyst for a solution that has 435 stakeholders.

How many communication channels exist in this project?

Options:

A.

188,790

B.

189,225

C.

94,395

D.

435

Expert Solution
Questions # 118:

Which of the following processes is used to make certain that the project team members are completing the project work according to the project plan?

Options:

A.

Project time management

B.

Project scope management

C.

Quality management plan

D.

Quality control

Expert Solution
Questions # 119:

You are coaching Marcy, a new business analyst for your organization, on business analysis processes. Marcy is concerned about the define solution scope process, especially the implementation approach element.

Which of the following statements best defines the implementation approach element for Marcy?

Options:

A.

The implementation approach is described in terms of the major features and functions that are to be included.

B.

The implementation approach defines major business and technical dependencies that impose constraints to the effort to deploy the solution.

C.

The implementation approach describes the new capabilities required to meet the business need.

D.

The implementation approach describes how the chosen solution approach will deliver the solution scope.

Expert Solution
Questions # 120:

When do change requests generally increase in a project?

Options:

A.

During the project's launch.

B.

Towards the beginning of the project.

C.

During the project scope management processes.

D.

Towards the end of the project.

Expert Solution