Questions # 71:

When should a Sprint Goal be created?

Options:

A.

It should have been created in the previous Sprint during Product Backlog refinement.

B.

It must be established before Sprint Planning in order to begin planning.

C.

A Sprint Goal is not mandatory in Scrum.

D.

At any time during the Sprint.

E.

During Sprint Planning.

Expert Solution
Questions # 72:

Select two ways in which technical debt impacts transparency. (Choose two.)

Options:

A.

When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.

B.

It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.

C.

As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.

D.

It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.

Expert Solution
Questions # 73:

The Development Team should have all the skills needed to:

Options:

A.

Turn Product Backlog items into an Increment of potentially releasable product functionality.

B.

Do all of the development work, except for specialized testing that requires additional tools and environments.

C.

Complete the project within the date and cost as calculated by the Product Owner.

Expert Solution
Questions # 74:

When must a Product Owner release each Increment? (Choose the best answer.)

Options:

A.

When it makes sense.

B.

When the Scrum Team finishes their work.

C.

Whenever the product is free of defects.

D.

After every Sprint, Without exception.

Expert Solution
Questions # 75:

What is the purpose of a Sprint Review?

Options:

A.

To take time to judge the validity of the project.

B.

To inspect the product increment with the stakeholders and collect feedback on next steps.

C.

To review the Scrum Team’s activities and processes during the Sprint.

D.

To build team sprint.

Expert Solution
Questions # 76:

Which of the following are true about the Product Owner role? (Choose two.)

Options:

A.

The Product Owner is one person.

B.

The Product Owner is accountable for ordering the Product Backlog.

C.

Multiple people can share the Product Owner role on a Scrum Team.

D.

The Product Owner role can be played by a committee or a team of people.

Expert Solution
Questions # 77:

The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)

Options:

A.

Inform the Product Owner’s functional manager.

B.

Stop the Sprint, send the Product Owner to a course and restart.

C.

Bring up the problem in the Sprint Retrospective.

D.

Coach the Product Owner in the values of Scrum and incremental delivery.

E.

Nominate a proxy Product Owner.

Expert Solution
Questions # 78:

Who starts the Daily Scrum?

Options:

A.

The person coming in last. This encourages people to be on time and helps to stay within the time-box.

B.

Whoever the Development Team decides should start.

C.

The person who has the token.

D.

The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

E.

The person who last broke the build.

Expert Solution
Questions # 79:

For which is the Scrum Master responsible?

Options:

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Expert Solution
Questions # 80:

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Options:

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.