Questions # 11:

Which 2 statements represent appropriate entries for the Development

Approach Definition?

Options:

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called 'WebMatrix' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Expert Solution
Questions # 12:

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Expert Solution
Questions # 13:

An external web developer is to be contracted to create the new coffee bar

insurance area on the existing web site. The chosen web developer will only

agree to work on a 'fixed price for a fixed specification' contract.

What action should the Project Manager take?

Options:

A.

Ensure the later elements of the project reflect the most valuable features

of the product being built by the contractor.

B.

Agree to a 'fixed price for a fixed specification' contract with a requirement

for the web developer to provide daily progress reports.

C.

Refuse to employ the chosen web developer as this is not an Agile

approach to project management.

D.

Divide the work into component parts to ensure the web developer is

focused on, and is paid to deliver, only what is specified for each

component.

Expert Solution
Questions # 14:

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Expert Solution
Questions # 15:

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Expert Solution
Questions # 16:

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

Options:

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Expert Solution
Questions # 17:

How should the Project Manager encourage the contractors to turn up on time?

Options:

A.

Place a penalty clause on all contractors for late arrival.

B.

Appoint Team Leaders to each of the electrical and plumbing teams.

C.

Encourage open and honest communication to re-establish an environment of trust.

D.

Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.

Expert Solution
Questions # 18:

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox A.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because the new requirement needs to be understood, built and delivered in this Timebox.

B.

Yes, because the Local Planning Authority Officer owns the justification for the new requirement.

C.

No, because this new requirement would NOT be included in the original Prioritised Requirements List and therefore does NOT need acceptance criteria to be defined.

D.

No, because the Business Visionary is responsible for defining acceptance criteria.

Expert Solution
Questions # 19:

Which 2 actions should the Workshop Facilitator take when preparing for the workshop?

Options:

A.

Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.

B.

Invite the Marketing Director to create a summary of the content they believe the system should hold and why.

C.

Assign ownership of the workshop to the Software Developer.

D.

Ask the IT Operations Manager to prepare the agenda for the workshop.

E.

Research other hotel reservation systems to form an opinion on what the content should be.

Expert Solution
Questions # 20:

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

Question # 20

Options:

Expert Solution
Viewing page 2 out of 6 pages