Questions # 101:

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

Options:

A.

Amount of work needed to complete a single user story

B.

Amount of work that can be accomplished by each team member

C.

Amount of work that can be accomplished in an iteration

D.

Amount of work that can be accomplished by the entire team

Expert Solution
Questions # 102:

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Expert Solution
Questions # 103:

What was the determining factor?

Options:

A.

Size and priority

B.

Minimum marketable features

C.

Release plan

D.

Sprint mapping

Expert Solution
Questions # 104:

In a project, the customer asks for a requirement that clearly deviates from the contract terms.

How should the contractor react?

Options:

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Expert Solution
Questions # 105:

What should the team do to effectively manage this?

Options:

A.

Rework the iteration scope to accommodate these requirements.

B.

Add these requirements into the product backlog for future consideration.

C.

Raise the discovery of these requirements as an issue, and escalate to management.

D.

Immediately start working on these requirements.

Expert Solution
Questions # 106:

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options:

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Expert Solution
Questions # 107:

A software development team is working in an environment in which increased competition, demanding customer expectations, and new technological developments pose significant challenges.

How should the team plan improvements to their product?

Options:

A.

Follow the project schedule created at the start of the project.

B.

Hold regular retrospectives and have team members commit to specific actions.

C.

Allow team members to choose improvement items and trust their judgment.

D.

Encourage team members to write code that is tightly coupled together.

Expert Solution
Questions # 108:

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

Options:

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Expert Solution
Questions # 109:

A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.

What should the agile lead do?

Options:

A.

Explain that the testable acceptance criteria are included in each story and it is necessary for the expert to collaborate with the developers, testers, and product owner for common understanding of the solution.

B.

Agree, and ask the developers to explain to the testers how the solution should perform for quality assurance. The testers will demonstrate to the stakeholders how the system should perform to gain acceptance.

C.

Agree, because the developers can copy and paste the requirements and include the technical specifications and performance criteria while writing the stories to save time.

D.

Explain to the project sponsor that the user stories should be assigned to the analysts, because they helped write the requirements and better understand them.

Expert Solution
Questions # 110:

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

Options:

A.

Obtain approval from the change control board to discontinue the component

B.

Ask the team to continue developing the component

C.

Ask the team to discontinue developing the component

D.

Request the sponsor's formal approval to discontinue the component

Expert Solution