Questions # 91:

Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

Options:

A.

Raise an impediment that resource tasks will be blocked and notify the Product Owner

B.

Ask the delivery manager for a temporary resource

C.

Ask the Scrum Master to assign that team member's tasks to the next available resource

D.

Assume the team member's tasks to meet iteration goals and notify the Product Owner

Expert Solution
Questions # 92:

During a backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog.

What should the team do?

Options:

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Expert Solution
Questions # 93:

A senior manager has asked an agile team to ensure that the data for the burndown charts are updated in real-time. However, the team is not comfortable with this approach as they think this is not productive.

What should the scrum master do?

Options:

A.

Ask the product owner to manage and share the metrics with appropriate stakeholders.

B.

Meet with requestors to agree and align on reporting requirements.

C.

Deny the request and explain the team's stance to the stakeholders.

D.

Work with the team to create the metrics requested by the stakeholders.

Expert Solution
Questions # 94:

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.

What should the agile practitioner do?

Options:

A.

Provide all information requested by the stakeholder

B.

Set expectations regarding the appropriate level of details requested during this stage

C.

Inform the stakeholder that no detailed documents are provided using agile practices

D.

Ask the team to supply the information to the stakeholder

Expert Solution
Questions # 95:

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

"Inspect and adapt" are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member's opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Expert Solution
Questions # 96:

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

Options:

A.

Lead time, throughput, and due date performance

B.

Work in progress limits, Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Expert Solution
Questions # 97:

An Agile team has received several new features to be added to the product backlog. The team is struggling to provide a reasonable estimate for feature development due to a lack of experience.

How should an experienced Agile practitioner assist the team?

Options:

A.

Add a task to the product backlog to allow the team time to investigate and experiment prior to estimating.

B.

Add a task to the product backlog to allow the team to apply a wideband Delphi estimation technique.

C.

Add a task to the product backlog to allow the team to apply planning poker to estimate the effort.

D.

Add a task to the product backlog to allow the team to apply a three-point estimation technique.

Expert Solution
Questions # 98:

What should the product owner have done differently?

Options:

A.

Demonstrated only the completed stories and seek stakeholder feedback

B.

Presented the budget situation and review the cost variance

C.

Reviewed the test results to gain confidence from the stakeholders

D.

Presented a demo of all the stories including the work in progress stories

Expert Solution
Questions # 99:

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

Options:

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team's time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

Expert Solution
Questions # 100:

An agile project manager is leading an international project involving a global team consisting of members from very different cultures, countries, and time zones. The agile project manager is aware that similar projects with distributed teams have led to serious conflicts.

What should the agile project manager do to promote trust and collaboration?

Options:

A.

Talk with the human resources (HR) department to select team members with similar backgrounds to eliminate conflict

B.

Collocate for team building to promote collaboration to build trust and improve communication.

C.

Promote a project charter with the project vision and purpose to help align the team.

D.

Promote a team charter with a set of norms rules and agreements to facilitate the work

Expert Solution