Questions # 121:

A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.

How should the project manager proceed?

Options:

A.

Consult with the product owner to prioritize the new work at a higher level.

B.

Consult with the project sponsor and project team to resolve the issue.

C.

Consult with the project team to rework the existing estimates.

D.

Consult with the product owner and project team.

Expert Solution
Questions # 122:

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?

Options:

A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.

B.

Request the team work overtime to get the work done on time and within the allocated budget.

C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.

D.

Review the contract documentation with the customer to clarify the specific agreed-upon budget amount.

Expert Solution
Questions # 123:

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Expert Solution
Questions # 124:

Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?

Options:

A.

Understand the physical and virtual communication needs of the team and plan agile events based on the majority of the team members' needs.

B.

Escalate with senior management and ensure that everyone on the project team is physically colocated for all planned agile events.

C.

Invest in technology-collaboration tools to enable effective communication and ensure a common understanding of the scope, issues, and solutions.

D.

Recognize the different communication styles of the stakeholders and take a vote on the best approach that will work for the team.

Expert Solution
Questions # 125:

An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.

Which method of communication would be most effective?

Options:

A.

Interactive communication

B.

Pull communication

C.

Interpersonal communication

D.

Push communication

Expert Solution
Questions # 126:

A business analyst has been assigned to optimize a process to deliver healthcare services to patients in a clinic. In creating a value stream map, what will the business analyst’s key observations include?

Options:

A.

Process breakdowns and workflow

B.

Wait times and cycle times

C.

Process maps and story points

D.

Activity sequences and earned value (EV)

Expert Solution
Questions # 127:

A software team is developing a product in an environment with increased uncertainty. Although there is a clear vision of the goals to be achieved, the product owner is not fully certain about how some of the product features should work.

How should the product owner address this situation?

Options:

A.

Improve the product testing and quality assurance skills among the team

B.

Facilitate more product planning sessions with the software team.

C.

Consider moving to a more predictive product development approach.

D.

Develop a prototype of the product to obtain feedback from users.

Expert Solution
Questions # 128:

An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.

What should the agile lead do to ensure the release will be on time for the fair?

Options:

A.

Reduce the scope of the release to meet the deadline.

B.

Deliver as many features as possible based on the new velocity.

C.

Extend the project timeline to accommodate the missing team member.

D.

Hire a new team member to replace the missing one.

Expert Solution
Questions # 129:

In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.

How should the project manager approach this project?

Options:

A.

Define all requirements so value can be added by delivering a high-level plan at the initiation phase.

B.

Suggest the Product Owner prioritize the work items by feature to maximize value.

C.

Ask the customer to define the requirements of all stakeholders and select the most valuable features.

D.

Ensure the client has a clear idea about the features and end product before the project starts.

Expert Solution
Questions # 130:

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, the junior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, the junior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

Options:

A.

Escalate the issue to the functional manager and request another team member with more experience.

B.

Ask the team to refer to the team charter on how to resolve this kind of impediment and help the team member.

C.

Coach the team by reminding them that a self-managed team requires everyone to be able to remove their impediments.

D.

Remind them that self-managed teams require everyone to be honest and supportive of one another to resolve impediments.

Expert Solution