Questions # 51:

How many roles make up the Project Board?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Expert Solution
Questions # 52:

What is the collective name for individuals or groups who may be affected by a project?

Options:

A.

Customers

B.

Project Support

C.

Stakeholders

D.

Team members

Expert Solution
Questions # 53:

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Expert Solution
Questions # 54:

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Options:

A.

Those with a financial interest in the project

B.

Those who will manage the project on a day-to-day basis

C.

Those who will specify the desired outputs of the project

D.

Those who will create the project's outputs

Expert Solution
Questions # 55:

Which two roles are linked by the Managing Product Delivery process?

Options:

A.

Corporate or programme management and Project Board

B.

Project Board and Project Manager

C.

Project Manager and Team Manager

D.

Team Manager and external supplier

Expert Solution
Questions # 56:

What product defines the reporting requirements between the Project Manager and Team Manager?

Options:

A.

Project Brief

B.

Product Description

C.

Team Plan

D.

Work Package

Expert Solution
Questions # 57:

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Options:

A.

Configuration Item Record

B.

Quality Register

C.

Highlight Report

D.

Checkpoint Report

Expert Solution
Questions # 58:

Which is NOT considered when defining risk tolerance?

Options:

A.

A Project Board's attitude towards risk taking

B.

The allocated risk budget

C.

An organization's risk appetite

D.

The amount of risk a Project Board considers acceptable

Expert Solution
Questions # 59:

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Expert Solution
Questions # 60:

What takes place during the Closing a Project process?

Options:

A.

The post-project benefits reviews are performed

B.

Ownership of the project's products is transferred to the customer

C.

An End Stage Report is prepared for the final stage

D.

The project closure notification is reviewed and approved