Questions # 61:

Which is NOT one of the PRINCE2 integrated elements?

Options:

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Expert Solution
Questions # 62:

What needs to be in place to ensure effective issue and change control?

Options:

A.

Configuration management system

B.

Manage by exception

C.

Quality planning

D.

Information needs for stakeholders

Expert Solution
Questions # 63:

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Options:

A.

Benefits

B.

Quality

C.

Risk

D.

Scope

Expert Solution
Questions # 64:

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

Options:

A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Expert Solution
Questions # 65:

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Options:

A.

quality

B.

supplier

C.

risk

D.

product

Expert Solution
Questions # 66:

When should the Project Board refer to corporate or programme management for a decision?

Options:

A.

The stage requires resources

B.

It is forecast that project level tolerance will be exceeded

C.

The Senior Supplier or Senior User needs to be changed

D.

Any request for change needs to be approved

Expert Solution
Questions # 67:

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Expert Solution
Questions # 68:

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Options:

A.

Directing a Project

B.

Controlling a Stage

C.

Managing a Stage Boundary

D.

Managing Product Delivery

Expert Solution
Questions # 69:

Why is it crucial that the Project Product Description clearly defines acceptance methods?

Options:

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Expert Solution
Questions # 70:

Which statement about the quality review technique is FALSE?

Options:

A.

It enables a check to be made on a product's fitness for purpose

B.

It defines the quality responsibilities of the project team

C.

It supports the management of future changes by providing a baseline for a product

D.

It is used to gain wider acceptance of a product by involving key interested parties