Questions # 91:

Why is a project brief produced?

Options:

A.

To act as a trigger for the 'starting up a project' process

B.

To record the how the project will communicate with its stakeholders

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the project board as a basis for reviewing the progress of a project

Expert Solution
Questions # 92:

What is a benefits management approach used to assess?

Options:

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Expert Solution
Questions # 93:

When should the level of tailoring be defined?

Options:

A.

During the initiation stage

B.

When reviewing what has been learned to date

C.

As a response to issues and risks experienced

D.

Before the project is triggered by the project mandate

Expert Solution
Questions # 94:

What should the 'managing product delivery' process ensure?

1. That the planned products meet their quality criteria

2. That the stage plan is kept up to date

3. That the project board is provided with progress information

4. That the planned products are delivered within tolerance

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Expert Solution
Questions # 95:

Which document should record the agreed amount of risk budget for a project?

Options:

A.

Project Brief

B.

Project Plan

C.

Risk Management Strategy

D.

Risk Register

Expert Solution
Questions # 96:

Which level of management sets the project level tolerances?

Options:

A.

Project board

B.

Team manager

C.

Corporate, programme management or the customer

D.

Project manager

Expert Solution
Questions # 97:

Which is a purpose of a Risk Register?

Options:

A.

Capture risks that may occur during the project

B.

Record how risk management activities will be undertaken on the project

C.

Record the risk tolerance for the project

D.

Capture issues which are impacting on the delivery of the project objectives

Expert Solution
Questions # 98:

Which describes a project benefit?

Options:

A.

A specialist product of the project

B.

The result of a change derived from using the project's products

C.

An uncertain result caused by project actions

D.

A measurable improvement resulting from an outcome

Expert Solution
Questions # 99:

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

Options:

A.

Enable the Project Board to decide whether or not to authorize the project

B.

Justify the continuing viability of the project

C.

Enable the Project Board to decide whether or not to authorize project closure

D.

Justify the initiation of a project

Expert Solution
Questions # 100:

What is the project manager role responsible for?

Options:

A.

Approving the completion of each management stage

B.

Ensuring that the project produces the required products

C.

Defining the project-level tolerances

D.

Verifying that the project gives value for money