Questions # 71:

What is an off-specification?

Options:

A.

A new requirement

B.

A quality tolerance

C.

A type of issue

D.

A major risk

Expert Solution
Questions # 72:

Which is a purpose of the Risk Register?

Options:

A.

Describe the risk management techniques and standards to be applied to the project

B.

Act as a central record of information relating to the identified risks for the project

C.

Act as a repository for informal issues

D.

List the responsibilities for achieving an effective risk management procedure

Expert Solution
Questions # 73:

Which are advantages of a clear end to a project?

1. No further costs will be incurred by the project

2. Project products will be transferred to operations and support

3. All benefits will have been achieved

4. The project brief will be re-baselined

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Expert Solution
Questions # 74:

Which is an objective of the 'initiating a project' process?

Options:

A.

To ensure that baselines are established and controlled

B.

To ensure that the business case is kept under review

C.

To ensure that the planned products are delivered within tolerances

D.

To ensure that user acceptance of the products is confirmed

Expert Solution
Questions # 75:

Identify the missing word in the following sentence.  

A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

Options:

A.

benefits

B.

dis-benefits

C.

issues

D.

risks

Expert Solution
Questions # 76:

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

Options:

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Expert Solution
Questions # 77:

How does the use of product descriptions support the 'focus on products' principle?

Options:

A.

By documenting the scope tolerance for the project

B.

By documenting the quality expected by the customer

C.

By documenting the costs for the product

D.

By documenting the delivery date for the product

Expert Solution
Questions # 78:

What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Expert Solution
Questions # 79:

According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

Options:

A.

Project board, project manager and project assurance roles

B.

Directing, managing and delivering levels

C.

Business, user and supplier interests

D.

Corporate, programme management or the customer parties

Expert Solution
Questions # 80:

Which risk response is applied on a pain/gain basis?

Options:

A.

Share

B.

Accept

C.

Exploit

D.

Enhance

Expert Solution