Questions # 111:

What is a purpose of the communication management approach?

Options:

A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties

Expert Solution
Questions # 112:

What is the minimum number of management stages required by PRINCE2?

Options:

A.

Two stages: to initiate and to deliver the project

B.

One stage: to cover the whole project

C.

Three stages: to initiate, to deliver and to close the project

D.

Four stages: to start, to initiate, to deliver and to close the project

Expert Solution
Questions # 113:

Why does the project board review the PID during an end stage assessment?

Options:

A.

To confirm that project controls are adequate for the remainder of the project

B.

To notify the commissioning organization that the project has been authorized

C.

To review summarized progress to date and decide what to do next with the project

D.

To ensure that post-project reviews of operational performance are planned

Expert Solution
Questions # 114:

What is the result of the change derived from using the project’s product?

Options:

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output

Expert Solution
Questions # 115:

Which is an assumption about the PRINCE2 customer/supplier environment?

Options:

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Expert Solution
Questions # 116:

Which statement about the length of management stages in a project is CORRECT?

Options:

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Expert Solution
Questions # 117:

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options:

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Expert Solution
Questions # 118:

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Expert Solution
Questions # 119:

How does PRINCE2 ensure that the specific management needs of an organization are met?

Options:

A.

By incorporating tailoring

B.

By mandating training

C.

By focusing on viability

D.

By representing best practice

Expert Solution
Questions # 120:

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

Options:

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Expert Solution