Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the PRINCE2 Certification Prince2-Foundation Questions and answers with ValidTests

Exam Prince2-Foundation All Questions
Exam Prince2-Foundation Premium Access

View all detail and faqs for the Prince2-Foundation exam

Viewing page 9 out of 14 pages
Viewing questions 81-90 out of questions
Questions # 81:

Which approach must be followed as a minimum requirement for applying the plans theme?

Options:

A.

Activity-based planning

B.

Product-based planning

C.

Agile

D.

Risk management

Expert Solution
Questions # 82:

Which is a minimum requirement for applying the organization theme?

Options:

A.

Each member of the project management team must have a written role description

B.

The roles of the project management team must be combined, wherever possible

C.

The project manager must be appointed from the supplier organization

D.

The frequency of communication to the project's stakeholders must be documented

Expert Solution
Questions # 83:

Which is a responsibility of a risk owner?

Options:

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Expert Solution
Questions # 84:

Why is the 'initiating a project' process used?

Options:

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Expert Solution
Questions # 85:

What is performed as part of the recommended risk management procedure?

Options:

A.

A budget to investigate issues is allocated

B.

Risk management practices are reviewed to ensure that they are performed effectively

C.

Information about risks to the projects is sent to project stakeholders

D.

Conflicts between the project and the programme board are resolved

Expert Solution
Questions # 86:

Which process is used to define how baselines will be established and controlled?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Initiating a project

D.

Starting up a project

Expert Solution
Questions # 87:

Which is an objective of the 'directing a project' process?

Options:

A.

To review and approve a project mandate

B.

To ensure corporate or programme management has an interface to the project

C.

To define how risks, issues and changes will be managed

D.

To obtain approval for completed products

Expert Solution
Questions # 88:

What must a PRINCE2 project demonstrate?

Options:

A.

Application of PRINCE2 principles

B.

Application of proper leadership skills

C.

Application of the activities in each process

D.

Application of tools appropriate for the industry

Expert Solution
Questions # 89:

Which is a purpose of the Risk theme?

Options:

A.

Establish a method for the implementation of continuous improvement during the project

B.

Identify, assess and control problems that have occurred

C.

Provide the Project Board with a time-driven control to capture all project risks

D.

Establish a cost-effective procedure to identify, assess and control risks

Expert Solution
Questions # 90:

How is the tailoring approach defined for a project?

Options:

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

Expert Solution
Viewing page 9 out of 14 pages
Viewing questions 81-90 out of questions