Projects are separated into phases or subprojects; these phases include:
Which baselines make up the performance measurement baseline?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Funding limit reconciliation is a tool and technique used in which process?
Inputs to the Plan Risk Management process include the:
Risk exists the moment that a project is:
Which is an output of the Collect Requirements process?
In Project Cost Management, which input is exclusive to the Determine Budget process?
Which of the following tools and techniques is used in the Verify Scope process?
Which process determines the risks that might affect the project?
Which provides the basic framework for managing a project?
Which is an output from Distribute Information?
Monte Carlo is which type of risk analysis technique?
What provides information regarding the ways people, teams, and organizational units behave?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Which of the following is an input to Develop Human Resource Plan?
Tools and techniques used for Plan Communications include the communication:
In which Process Group are lessons learned documented?
Which of the following is an output of Direct and Manage Project Execution?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Change request status updates are an output of which process?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which tool or technique is used in Manage Stakeholder Expectations?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which technique helps to determine the risks that have the most potential impact on a project?
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Which of the following statements is true regarding project and product lifecycles?
Which of the following is an example of the simplest fixed-price contract?
Which of the following is a tool or technique of the Define Activities process?
What is a tool to improve team performance?
Types of internal failure costs include:
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Which of the following is an information gathering technique in Identify Risks?
Which of the following correctly explains the term "progressive elaboration'?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Which process should be conducted from the project inception through completion?
A project charter is an output of which Process Group?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
Which type of risk diagram is useful for showing time ordering of events?
Which of the following strategic considerations often results in project authorization?
What does a CPI value greater than 1.0 indicate?
Which of the following factors is lowest at the start of the project?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
The definition of operations is a/an:
Project contracts generally fall into which of the following three broad categories?
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?