Questions # 401:

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Expert Solution
Questions # 402:

The Identify Stakeholders process is found in which Process Group?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Expert Solution
Questions # 403:

Which tool or technique is used to manage change requests and the resulting decisions?

Options:

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Expert Solution
Questions # 404:

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Expert Solution
Questions # 405:

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Expert Solution
Questions # 406:

An input to Develop Project Charter is a/an:

Options:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

Expert Solution
Questions # 407:

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

Options:

A.

Project

B.

Scope

C.

Contract

D.

Program

Expert Solution
Questions # 408:

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Expert Solution
Questions # 409:

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Expert Solution
Questions # 410:

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Expert Solution
Questions # 411:

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Expert Solution
Questions # 412:

The process to ensure that appropriate quality standards and operational definitions are used is:

Options:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Expert Solution
Questions # 413:

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Expert Solution
Questions # 414:

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Expert Solution
Questions # 415:

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Expert Solution
Questions # 416:

An output of the Direct and Manage Project Work process is:

Options:

A.

Deliverables.

B.

Activity lists.

C.

A work breakdown structure.

D.

A scope statement.

Expert Solution
Questions # 417:

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Expert Solution
Questions # 418:

The completion of the project scope is measured against the:

Options:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Expert Solution
Questions # 419:

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Expert Solution
Questions # 420:

Which of the following is a tool or technique used in the Determine Budget process?

Options:

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Expert Solution
Questions # 421:

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Expert Solution
Questions # 422:

Which characteristics do effective project managers possess?

Options:

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Expert Solution
Questions # 423:

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Expert Solution
Questions # 424:

Administer Procurements is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Closing

Expert Solution
Questions # 425:

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Options:

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Expert Solution
Questions # 426:

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Expert Solution
Questions # 427:

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Expert Solution
Questions # 428:

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Expert Solution
Questions # 429:

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Expert Solution
Questions # 430:

Which of the following is a group decision-making technique?

Options:

A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Expert Solution
Questions # 431:

Which statement correctly describes the value of a business case?

Options:

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Expert Solution
Questions # 432:

The probability and impact matrix is primarily used to:

Options:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Expert Solution
Questions # 433:

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Expert Solution
Questions # 434:

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Expert Solution
Questions # 435:

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Expert Solution
Questions # 436:

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

Options:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Expert Solution
Questions # 437:

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Expert Solution
Questions # 438:

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Expert Solution
Questions # 439:

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Expert Solution
Questions # 440:

At the end of the project, what will be the value of SV?

Options:

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Expert Solution
Questions # 441:

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Expert Solution
Questions # 442:

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Expert Solution
Questions # 443:

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Expert Solution
Questions # 444:

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Expert Solution
Questions # 445:

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Expert Solution
Questions # 446:

One of the objectives of a quality audit is to:

Options:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Expert Solution
Questions # 447:

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Expert Solution
Questions # 448:

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Options:

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Expert Solution
Questions # 449:

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Expert Solution
Questions # 450:

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

Options:

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (T&M)

D.

Cost Plus Incentive Fee Contract (CPIF)

Expert Solution