Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the PMI PgMP Questions and answers with ValidTests

Exam PgMP All Questions
Exam PgMP Premium Access

View all detail and faqs for the PgMP exam

Viewing page 12 out of 14 pages
Viewing questions 111-120 out of questions
Questions # 111:

Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?

Options:

A.

Work breakdown structure

B.

Program network diagram

C.

Program scope baseline

D.

Activity list

Expert Solution
Questions # 112:

Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.

What should program A’s program manager update and review first with the stakeholders?

Options:

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan

Expert Solution
Questions # 113:

After taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.

Based on this information, the program manager determines which of the following?

Options:

A.

The schedule is US$30,000 under budget

B.

The cost is US$20,000 under budget

C.

The schedule is US$10,000 over budget

D.

The cost is US$20,000 over budget

Expert Solution
Questions # 114:

Your program has a budget at completion of $1,550,000 and is expected to last one year.

Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Options:

A.

The schedule is performing worse because the SPI is .90

B.

The cost is performing worse because the EAC is $1,611,111.

C.

The schedule is performing worse because the SV is -$27,500.

D.

The cost is performing worse because the CPI is .96.

Expert Solution
Questions # 115:

Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

Options:

A.

Deadlines for project milestones

B.

Building codes

C.

A predetermined program budget

D.

Weather

Expert Solution
Questions # 116:

You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Options:

A.

Program administrative closure

B.

Enterprise environmental factors

C.

Closing processes

D.

Organizational process assets

Expert Solution
Questions # 117:

What does RACI stand for?

Options:

A.

Responsible, Account, Confirm, Inform

B.

Responsible, Accountable, Consult, Inform

C.

Roles, Accountable, Confirm, Inform

D.

Roles, Action, Consult, Inform

Expert Solution
Questions # 118:

You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

Options:

A.

Finish on constraints

B.

Discretionary dependencies

C.

Mandatory dependencies

D.

Benefits management dependencies

Expert Solution
Questions # 119:

You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?

Options:

A.

Determine the time and cost of researching the issue for resolution.

B.

Record the issue in the issue log.

C.

Document the issue in the lessons learned.

D.

Communicate with the stakeholders that you are addressing the issue.

Expert Solution
Questions # 120:

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

Options:

A.

Certify contract completion

B.

Conduct a procurement audit to review the procurement process

C.

Assess all contracts to ensure all agreed conditions are met

D.

Review contract management plan for completeness

Expert Solution
Viewing page 12 out of 14 pages
Viewing questions 111-120 out of questions