Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the PMI PgMP Questions and answers with ValidTests

Exam PgMP All Questions
Exam PgMP Premium Access

View all detail and faqs for the PgMP exam

Viewing page 8 out of 14 pages
Viewing questions 71-80 out of questions
Questions # 71:

After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise’s

investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.

What should the program manager do to address this risk with the program sponsor and governance board?

Options:

A.

Share the concerns with the program sponsor to confirm understanding of the new development. Next, update the program budget, implementation plan, and risk management plan for governance board approval.

B.

Update the component project’s risk register, issue log, implementation plan, and risk management plan.

Next, meet with the program sponsor to revise the program budget, implementation plan, and risk management plan for governance board approval.

C.

Revise the program budget, and implement the component project by managing it closely to recover the month-long delay. Next, update the component’s project and risk management plans for governance board approval.

D.

Update the program budget, and task the component project manager with implementing the plan. Next, submit a change order for approval to apply more resources to reduce the larger program’s risk profile.

Expert Solution
Questions # 72:

You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of

the schedule control process except for which one?

Options:

A.

Stakeholder communication information

B.

Schedule variances

C.

Program schedule updates

D.

Change requests

Expert Solution
Questions # 73:

A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components’ strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools.

Which of the following must be addressed?

Options:

A.

Program performance monitoring and controlling

B.

Program management information system (PMIS)

C.

Program delivery management

D.

Program roadmap

Expert Solution
Questions # 74:

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template, while others prefer another.

How should the program manager decide which template is appropriate?

Options:

A.

Review the issue with the program management office (PMO) to determine which template to use.

B.

Review the issue with the project managers and come to mutual agreement on which template to use.

C.

Meet with the program governance board to select an appropriate template.

D.

Allow the component project managers to use their preferred templates.

Expert Solution
Questions # 75:

A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

Options:

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

Expert Solution
Questions # 76:

During program execution, how does a program manager ensure that benefits are being realized in accordance with program governance?

Options:

A.

By reviewing the benefits management plan

B.

By updating the benefits register

C.

By conducting benefits analysis and planning

D.

By reviewing the program business case

Expert Solution
Questions # 77:

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Options:

A.

Operational transfer plan

B.

Program transition plan

C.

Benefits transfer plan

D.

Program closure plan

Expert Solution
Questions # 78:

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.

How should the program manager demonstrate the program's progress?

Options:

A.

Define the key performance indicators (KPIs) for the program's outcome.

B.

Invite the key stakeholder to review the program charter and the program objectives.

C.

Provide additional program performance reports to the key stakeholder.

D.

Maintain the benefits register and provide it to the key stakeholder.

Expert Solution
Questions # 79:

You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

Options:

A.

Avoidance

B.

Mitigation

C.

Transference

D.

Enhancing

Expert Solution
Questions # 80:

Which of the following statements are true regarding the Monitoring and Controlling Program Risks process? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Risk Monitoring and Control is an ongoing process for the life of the program.

B.

Planned risk responses should be continuously monitored for new and changing risks.

C.

Monitoring reduces the impact of risk by identifying, analyzing, reporting, and managing risks on a continuous basis.

D.

It is the process of selecting the most suitable response to reduce the threats to the program objectives.

Expert Solution
Viewing page 8 out of 14 pages
Viewing questions 71-80 out of questions