Questions # 141:

The project lead of a newly created agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Expert Solution
Questions # 142:

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Expert Solution
Questions # 143:

A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals. What should the scrum master mention at the next retrospective?

Options:

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

Expert Solution
Questions # 144:

While struggling to take ownership of delivery an agile team fails to keep up with its sprint commitments What should the agile coach do?

Options:

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation