Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Pass the PMI ACP PMI-200 Questions and answers with ValidTests

Exam PMI-200 All Questions
Exam PMI-200 Premium Access

View all detail and faqs for the PMI-200 exam

Viewing page 3 out of 15 pages
Viewing questions 21-30 out of questions
Questions # 21:

The agile team disagrees with the business stakeholders on completing some epics What could help eliminate misunderstandings?

Options:

A.

Agree on requirements with all stakeholders

B.

Begin planning every four iterations

C.

Consider previous sprint demo feedback when planning the next sprint

D.

Include the reasons for the project in the contract

Expert Solution
Questions # 22:

During refinement, the team tester has a question about part of the acceptance criteria for a given user story. Who should clarify the acceptance criteria?

Options:

A.

The sponsor, since they understand the business value.

B.

The scrum master, since they coordinate with the team and define the acceptance criteria.

C.

The product owner, since their vision is the basis for the acceptance criteria.

D.

The developer, since they write the code that would be tested.

Expert Solution
Questions # 23:

Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.

What should the agile practitioner do?

Options:

A.

Review established ground rules with the team

B.

Ask team members specific questions to identify the cause

C.

Encourage the team to continue working to maintain the iteration's schedule

D.

Meet with the product owner and stakeholders to discuss the issue

Expert Solution
Questions # 24:

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the scrum master do?

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the scrum master do?

Options:

A.

Report the issue to the product owner and request help.

B.

Let the new release manager participate in the daily standup.

C.

Invite the new release manager to the sprint demo and ask for help.

D.

Send a status report to the release manager highlighting the issue.

Expert Solution
Questions # 25:

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.

What should the agile coach do?

Options:

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Expert Solution
Questions # 26:

During a team meeting members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks which has lowered motivation. What should the agile practitioner do?

Options:

A.

Organize a team-building activity to improve team morale

B.

Have team members work in pairs to learn from each other and develop new skills

C.

Ask team members to perform a value stream analysis of their activities.

D.

Add more resources to the team to help with the tasks

Expert Solution
Questions # 27:

An agile project manager is planning the initial scope, schedule and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

Options:

A.

Lead time, throughput and due date performance

B.

Work in progress limits Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Expert Solution
Questions # 28:

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Expert Solution
Questions # 29:

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes detailed design plan

D.

Product vision, business objectives, timeframes

Expert Solution
Questions # 30:

After conducting the second retrospective with project stakeholders, the customer expresses frustration. The customer wants a more predictable roadmap for the delivery of features and functionalities.

How should the project manager respond to the customer?

Options:

A.

Explain to the customer that an agile approach requires re-prioritization at the beginning of each sprint, so it is not possible to provide a roadmap.

B.

Ask the customer to develop a roadmap the team can follow for future delivery.

C.

Work with the customer to understand which user stories will deliver the best business value, re-prioritize the backlog, and share it with the customer to provide release plans.

D.

Work with the product owner to develop a tentative roadmap for the customer but explain that it is always subject to change.

Expert Solution
Viewing page 3 out of 15 pages
Viewing questions 21-30 out of questions