A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
How should the project manager respond’
While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves
What should the project manager do?
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations
What should the project manager do?
A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
What should the project manager do?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?
A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company
What should the project manager do first?
During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?
A team is ready to start working on a project with a customer who was very difficult to work with in the past because the customer was unable to describe exactly what they wanted What approach should the project manager take to remove this impediment?
The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization
How should the project manager handle the different stakeholders?
A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take'? (Choose two)
During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible
What approach should be used in this situation?
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.
What two actions can the project manager take to be more cost effective? (Choose two)
A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.
What action should the project manager take to motivate the project team's performance?
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members
What should the project manager do?
During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version
How can the project manager prevent this outcome in the new project?
A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval
How should the project manager approach this problem?
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?
Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?
Drag the items on left side to the matching term within the correct project.

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?
A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule
What should the project manager do to keep the project on schedule while still meeting project objectives'?
According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project
What should the project manager do?
During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks
Drag each risk type on the left to its correct example on the right

A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished
How should the project manager approach this situation?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project's success?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done
What kind of leadership style should the project manager use at this stage?
A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next
Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)
Drag the to the correct scenario on the right

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?
A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented
What should the project manager do?
A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?
A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.
What should be the project manager's next steps?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings
How should the project manager handle this moving forward?
A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component
What should the project manager have done to prevent this delay from happening?