Questions # 401:

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?

Options:

A.

Project sponsors

B.

Other project managers

C.

Business unit managers

D.

Program managers

Expert Solution
Questions # 402:

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

Options:

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

Expert Solution
Questions # 403:

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to

water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Expert Solution
Questions # 404:

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

Options:

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

Expert Solution
Questions # 405:

A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?

Options:

A.

Conduct a performance review and define and document the goals for the team member.

B.

Clarify decisions and request that the project team follows the project manager's decisions.

C.

Understand what the team member wants and find possible opportunities to address it.

D.

Remove existing ground rules and create new ground rules that support the project manager.

Expert Solution
Questions # 406:

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

Options:

A.

Move the task to the next sprint.

B.

Ask the team member to bring up the concern in the next daily meeting.

C.

Send an email explaining the issue to all team members.

D.

Reassign the task to another team member.

Expert Solution
Questions # 407:

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?

Options:

A.

Assess the impact of the stakeholder and engage properly.

B.

Escalate the stakeholder issue to the project sponsor.

C.

Develop a specific communications strategy for this stakeholder.

D.

Use interpersonal skills to gain stakeholder engagement.

Expert Solution
Questions # 408:

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

Options:

A.

Ask the experienced members to lead the junior members to facilitate skill transfer.

B.

Encourage team members to focus on delivering results with their specialized skills.

C.

Organize networking sessions to allow the team members to get to know one another.

D.

Ask the team to self-organize and escalate any issues to the project manager.

Expert Solution
Questions # 409:

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

Options:

A.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert's availability within the organization on an as-needed basis.

C.

Develop the team member's capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

Expert Solution
Questions # 410:

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

Options:

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

Expert Solution
Questions # 411:

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

Options:

A.

Increase the frequency of updates given to this stakeholder.

B.

Inform the team member to stop sending any further updates to the stakeholder.

C.

Raise this issue to the project sponsor in the next project status review meeting.

D.

Review this stakeholder's communication requirements.

Expert Solution
Questions # 412:

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Expert Solution
Questions # 413:

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

Options:

A.

Forward the client's request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

Expert Solution
Questions # 414:

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

Options:

A.

Escalate the team member's disruptive behavior to their functional manager.

B.

Collaborate with the team to arrive at team ground rules and publish the rules to the team.

C.

Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.

D.

Request team members document their decisions independently and share with each other.

Expert Solution
Questions # 415:

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

Options:

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

Expert Solution
Questions # 416:

A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to

reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project

manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide

upon the most effective way to communicate progress.

What should the project manager do?

Options:

A.

Send weekly emails to each stakeholder providing them with the project's progress.

B.

Ask the project sponsor to disseminate project progress across the organization's stakeholders.

C.

Set up an intranet site and allow stakeholders to access the relevant project information.

D.

Divide up the organization among the project team to provide direct project updates.

Expert Solution
Questions # 417:

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Expert Solution
Questions # 418:

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

Options:

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.

The mentor will be immediately available to take over the project if there are problems or project delays.

D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

Expert Solution
Questions # 419:

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

Options:

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

Expert Solution
Questions # 420:

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?

Options:

A.

Plan for continuous validation of the product.

B.

Discuss adding business scenario tests with the customer.

C.

Discuss adding additional test cases with the product owner.

D.

Add more test scenarios based on the issues found.

Expert Solution
Questions # 421:

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?

Options:

A.

Ask the project management office (PMO) to support and review all deliverables.

B.

Log the issue in the risk register and the issue log.

C.

Assign a technical writer to the project.

D.

Develop a standard for document quality control.

Expert Solution
Questions # 422:

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Options:

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Expert Solution
Questions # 423:

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Expert Solution
Questions # 424:

A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the

team member's emotional situation has affected the rest of the team's performance.

How should the project manager handle this situation?

Options:

A.

Help all team members learn to deal with their emotions by building a culture of empathy.

B.

Separate the key team member and replace them while they emotionally recover.

C.

Meet with the team to discuss how to handle the performance problem.

D.

Ask the human resources (HR) department for their support providing emotional help.

Expert Solution
Questions # 425:

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

Options:

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

Expert Solution
Questions # 426:

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

Options:

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.

A hybrid approach will allow the project manager to revise the product specifications.

D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Expert Solution
Questions # 427:

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

Question # 427

Options:

Expert Solution
Questions # 428:

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

Options:

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver

value incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the

project.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end

of the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

Expert Solution
Questions # 429:

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Question # 429

Options:

Expert Solution
Questions # 430:

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

Options:

A.

Invite the stakeholders to the retrospective meetings.

B.

Invite the stakeholders to the sprint review meetings.

C.

Hold a meeting every 2 weeks with the stakeholders.

D.

Negotiate by sending an informative email to stakeholders.

Expert Solution
Questions # 431:

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

Options:

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

Expert Solution
Questions # 432:

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

Options:

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Expert Solution
Questions # 433:

An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

Options:

A.

Require that all team members be physically present for the weekly project review.

B.

Offer the team member an incentive to stay until the end of the project.

C.

Replace the team member with someone who has similar qualifications and is located closer.

D.

Set up a weekly video conference to monitor the progress of the team member's work.

Expert Solution
Questions # 434:

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

Options:

A.

Start working on the resource management plan in order to identify the best team for the project.

B.

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.

Review the competitor's app to understand the functionalities that the project scope should consider.

D.

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Expert Solution
Questions # 435:

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

Options:

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Expert Solution
Questions # 436:

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

Options:

A.

Establish the team ground rules and share them with the team for strict adherence.

B.

Copy the ground rules established by another project and provide them to the teams.

C.

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.

D.

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Expert Solution
Questions # 437:

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

Options:

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Expert Solution
Questions # 438:

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

Options:

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

Expert Solution
Questions # 439:

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

Options:

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Expert Solution
Questions # 440:

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Schedule the meeting at the end of the day to accommodate everyone.

B.

Ignore the situation since the team member is accomplishing their deliverables.

C.

Reinforce the ground rules for standup meetings with the entire team.

D.

Speak with the team member directly to reinforce the ground rules.

Expert Solution
Questions # 441:

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

Options:

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Expert Solution
Questions # 442:

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

Options:

A.

Dedicate the next sprint to completing the missing details.

B.

Apply fast-track techniques to work on the missing details in parallel,

C.

Continue iterating and monitoring quality aspects sprint by sprint.

D.

Create a new risk entry for the delay in the risk management plan.

Expert Solution
Questions # 443:

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Options:

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Expert Solution
Questions # 444:

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

Options:

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Expert Solution
Questions # 445:

A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.

What should the agile project manager do to engage the stakeholder in the project?

Options:

A.

Present the project management plan to the stakeholder and reassure them that they will receive regular project updates.

B.

Introduce the stakeholder to the project team and invite them to the next iteration review meeting with the IT team.

C.

Build trust with the stakeholder by keeping project commitments and use demo sessions to gather feedback and realign goals.

D.

Use stakeholder mapping to document the level of influence and interest for the next iteration planning meeting.

Expert Solution
Questions # 446:

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Expert Solution
Questions # 447:

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Expert Solution
Questions # 448:

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Options:

A.

Inform the project sponsor about the problem faced by the team.

B.

Ask the product owner to write the specifications for the related user story.

C.

Organize an early retrospective with the team to analyze the problem.

D.

Facilitate a problem-solving session with the team to analyze the problem.

Expert Solution
Questions # 449:

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Expert Solution
Questions # 450:

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

Options:

A.

Forming

B.

Mourning

C.

Storming

D.

Norming

Expert Solution