A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?
In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches
What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings
How should the project manager handle this?
A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion
What are two issues that these actions by the project manager could cause? (Choose two)
A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.
What should the project manager do?
A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget
What should the project manager do next?
The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable
What personality indicators should the project manager consider when determining what communication style to use with this team member?

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.
What training should the project manager choose for their team to help with this situation?
The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?
A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end
What action should the project manager take to motivate the project team’s performance?
A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects
What should the project manager do?
During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.
What should the project manager do first?
A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the
main stakeholders, but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria
defined by the product owner and does not understand what went wrong.
How should the project manager mitigate the product rejection?
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two
projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.
What kind of leadership style should the project manager utilize for the current project?
A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.
Match the following common terms with their explanations that evaluate the buffers or constraints.

In a product development project, the project manager is constantly receiving complaints from stakeholders about functionalities being delivered, but not required by the business departments. The project sponsor wants to know if the project resources are being used effectively.
What should the project manager have done to avoid delivering work that is not adding value to the business?
An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.
What should the project manager do next?
A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.
What should the project manager do?
A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is
identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact
on the project outcomes.
What should the project manager do next?
A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.
What should the project manager do first to address the SPI trend?
A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of
the team members were stressed due to over commitments.
What should the project manager do?
A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project
manager is confused since the entire team is located in the same time zone and believes there are other factors at play.
What should the project manager do next?
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.
What should the project manager establish first in the project governance structure?
A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?
An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are
likely to require this knowledge in the future.
What should the agile project manager do?
A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources
and has appointed a project manager.
What should the project manager recommend that the CEO do first?
A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the
importance of the project meeting the company's strategy, investment, and compliance requirements.
What should the project manager do?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase, the business stakeholders were unable to understand the feature integration with the product and raised concerns.
What can the project manager do to demonstrate the feature integration?
All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.
What should the project manager do to prevent these delays?
A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables. How should the project manager respond?
A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,
the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.
What should the project manager have done to prevent this from happening?
A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.
What should the project manager do to lead the project?
A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.
What should the project manager do next?
A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted
that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.
What should the project manager have done to avoid this situation?
In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.
What should the project manager do?
A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization
and asks the project manager to pay attention to changes that can affect the project.
Which action should the project manager take to identify changes that may affect the product?
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.
What should the project manager do next?