During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?
A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.
What should the project manager have done to avoid this situation?
A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.
What should the project manager do?
In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market
while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.
What should the project manager do to avoid a reoccurrence of this scenario?
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to
outline situations, solutions, results, and suggestions.
How should the project manager use the information collected?
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle
What should the project manager do next?
A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one
member reported an impediment that requires collaboration from an expert who is assigned to another project.
What should the project manager do first in this situation?
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the
company’s competitive advantage. What should the project manager do?
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?
An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.
What should the servant leader do?
A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager
has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management
competencies. The project manager explains that the exiting team members were lazy.
What should the project manager do to prevent this high turnover rate from continuing?
A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?
An experienced project team member always points out the issues of other team members during meetings. The other team members feel that
the experienced team member is deflecting their own issues in meetings.
What should the project manager do?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.
Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)
A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
What should the project manager recommend?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.
What should the project manager do to ensure value is delivered quickly?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team
to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three)
A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?
The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could
resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the
project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.
At what point did the project manager move the risk from the risk register to the issue log?
A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.
What conclusion should the project manager come to with regard to the product owner's statement?
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?
A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical
complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.
What should the project manager do?
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.
What should the project manager do to avoid this situation in the future?
A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools.
What should the project manager do to ensure team members are committed to project success?
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is
informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.
What should the project manager do first?
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a
dependency missing between:
+ Test the product
+ Release to customer
According to the quality management plan, the product must be tested before being released.
How should the project manager enter this dependency?
A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the
processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager
reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager
confirms that the team is following the processes exactly.
What should the project manager do?
During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain
feedback from on project deliverables. What should the project manager do?
During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.
What should the project manager do next?
A project team is transitioning to agile. During the sprint retrospective, a new member of the team proposed a more structured approach for capturing requirements that would improve clarity and reduce rework. Although the team members are happy to use it, changing the way business requirements are described requires agreement from an influential business manager.
What should the project manager do?
A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns
that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.
Which action should the project manager take to procure the vehicles?